BACON MANITO I & II GEOTHERMAL STEAMFIELDS PROJECT

DESCRIPTION:

The project includes two (2) power plants (Bacman I & II) with a total installed capacity of 150 MW utilizing geothermal sources from Palayan, Cawayan and Botong sectors in the Greater Bacman Area of Albay and Sorsogon provinces.

The power plant components were built, owned and operated by the National Power Corporation (NPC).

Electricity generated from these power plants was being supplied to the Luzon grid via high-voltage overhead transmission lines.

PROJECT SITE:

Albay and Sorsogon Provinces, Region 5

STATUS:

Normal Operation

Power plant components:
Power Plant Installed Commencement Capacity of Operation
Bacman I 1993 110 MW
Bacman II (Cawayan) 1994 20 MW
Bacman II (Botong) 1998 20 MW